Michigan Multilane Lane Closure Traffic Control Plan

Close one lane of a four-or-more-lane, non-divided road and traffic merges past the work behind a taper and an arrow board — MUTCD TA-30. The merging taper is the long one, and it grows fast with speed. Here is what the engine computes for Michigan at 25, 35, 45, and 55 mph.

Real MUTCD dimensions, a title block, and a printable sheet — no account, no cost.

Build this plan free — takes about 2 minutes

Computed MUTCD dimensions

Governing typical application: TA-30 — Lane Closure on a Multilane Street. Assumptions: urban collector, 4 through lanes, 12 ft lanes, 12 ft lateral offset, 100 ft work space, short-term duration. Rule set MUTCD 11th Ed. + 50-state/DC adoption layer + ID/ACHD profiles, rule set 2026-08 rev 4.

MUTCD 11th Edition Part 6 values computed by the TCP Builder engine.
Posted speedTaper length (merging)Advance signs A / B / CLongitudinal bufferDevice spacing taper / tangentChannelizing devices
25 mph125 ft100 ft / 100 ft / 100 ft155 ft25 ft / 50 ft18
35 mph245 ft250 ft / 250 ft / 250 ft250 ft35 ft / 70 ft18
45 mph540 ft350 ft / 350 ft / 350 ft360 ft45 ft / 90 ft24
55 mph660 ft350 ft / 350 ft / 350 ft495 ft55 ft / 110 ft23

What applies in Michigan

Agency rule set
State of Michigan (MUTCD as adopted)
MUTCD adoption
Publishes its own state MUTCD (cross-checked against a second source)
State manual
Michigan MUTCD (MMUTCD), published by MDOT

Printed on every Michigan sheet:

  • Michigan publishes its own MUTCD — the Michigan MUTCD (MMUTCD), published by MDOT; this sheet uses National MUTCD default values as a planning baseline — the state manual controls and must be checked before submittal.

This rule set holds no Michigan-specific permit form, review time, or closure-hour restriction, so none is shown. Those are set by whoever owns the road — state DOT, county, city, or highway district — and have to come from them.

Governing citation: Michigan — MUTCD adoption recorded as: state MUTCD published (Michigan MUTCD (MMUTCD), published by MDOT). Bucket taken from secondary compilations of 11th-Edition state MUTCD adoption current to mid-2026; FHWA’s own state adoption listing was unreachable from the build environment and has not been checked directly. Cross-checked against a second independent source. Michigan appears on the long-standing list of states publishing their own MUTCD. This rule set asserts no Michigan-specific numeric requirement; adoption status best-effort — verify against FHWA’s state adoption listing (“MUTCD information by State”) and the state DOT before submittal.

Questions people actually ask

How long is the merging taper for a lane closure in Michigan?

It depends on posted speed and the width being closed. MUTCD uses L = W·S²/60 below 45 mph and L = W·S at 45 mph and above. The table above computes it for a 12 ft lane at four speeds; the builder recomputes it for your actual lane width.

Do I need an arrow board?

For a stationary lane closure on a multilane road, yes — the arrow board goes at the beginning of the merging taper. It supplements the channelizing devices and the advance signs; it does not replace either.

Does this cover freeway and divided-highway closures?

No, and the tool refuses rather than approximating. TA-30 assumes a non-divided two-way road with four or more through lanes. Divided highways and freeways run off their own plates and need a sheet designed for them.

Real MUTCD dimensions, a title block, and a printable sheet — no account, no cost.

Build this plan free — takes about 2 minutes

DISCLAIMER — READ BEFORE USE

This traffic control plan was generated by an automated tool for planning and reference purposes only. It is based on the MUTCD 11th Edition Part 6 typical applications and the agency rule set selected above. It is not a certified, sealed, or professionally engineered document and has not been reviewed against actual field conditions at this site. It must be reviewed, adapted to field conditions, and approved by a qualified person — and, where required, by the permitting agency and/or a licensed Professional Engineer — before use. Field conditions govern. The user is solely responsible for work-zone safety, for conformance with all applicable federal, state, and local requirements, and for obtaining all required permits. PM Axsus disclaims all liability arising from use of this document.

Other plan types in Michigan